Project Management Asked by Peter on August 2, 2020
In MS Project (current version), I have the following task setup and can’t find a solution:
Short translation for columns:
Vorgangsname = Taskname
Arbeit = Work
Dauer = Duration
Anfang = Beginning
Ende = End
Not visible in the screenshot: Both tasks have the fixed day 2015-10-05 (Monday) and the resource-availability is 50% (global setting).
My question is: How can both tasks begin on the same day without a resource-conflict? My suggestion is, to change the percentage of the resource-availability per task, but I don’t know where to find that setting.
The problem here seems to be that the resource availability is only available at 50% - so if the resource works an 8 hr day, then he or she is only available for 4 hours of that day. Increase this percentage to 100% if the resource is available for 1 full day.
Correct answer by Treasa on August 2, 2020
You can change the allocation of resources in units.
To do so:
And done.
Answered by FRED G on August 2, 2020
7 Asked on October 26, 2021 by jean-tabaka
agile business case leadership organizational structure scrum
4 Asked on October 26, 2021 by padu-merloti
3 Asked on October 26, 2021
3 Asked on October 26, 2021 by thabo
3 Asked on October 26, 2021 by stockoverflow111
1 Asked on October 26, 2021 by avish12
4 Asked on October 26, 2021
3 Asked on October 26, 2021 by bash717
1 Asked on October 26, 2021 by user4434
1 Asked on October 26, 2021 by jason-h
1 Asked on October 26, 2021
1 Asked on January 23, 2021 by suren-n
6 Asked on January 12, 2021 by hamena314
3 Asked on January 9, 2021
2 Asked on December 14, 2020 by ha9u63ar
2 Asked on August 2, 2020 by peter
Get help from others!
Recent Questions
Recent Answers
© 2022 AnswerBun.com. All rights reserved. Sites we Love: PCI Database, MenuIva, UKBizDB, Menu Kuliner, Sharing RPP