Showing successor task names in MS Project

Project Management Asked by Hedge on December 12, 2021

I’m new to MS Project. I have a view where I want to get a list of successors for a list of tasks. I’ve added the Successors column and that gives me the list I want, but it’s their unique IDs. Is there a way to get the same list but it’s their task names instead of their unique IDs?

One Answer

With the Task Form shown in the bottom pane, right-click on any part of the Task Form and select "Predecessors and Successors." The list of task successor relationships will be shown on the right side of the form.

Answered by Tom Boyle on December 12, 2021

Add your own answers!

Related Questions

How to combine BPM and Scrum?

1  Asked on October 26, 2021 by asen

     

Different Resource Available Hours

0  Asked on October 26, 2021

 

Strict or pragmatic Scrum?

9  Asked on October 26, 2021 by bastian-spanneberg

   

How to handle big stories / epics in Scrum?

9  Asked on October 26, 2021 by bartosz-rakowski

     

Ask a Question

Get help from others!

© 2023 AnswerBun.com. All rights reserved. Sites we Love: PCI Database, UKBizDB, Menu Kuliner, Sharing RPP